KEY PROJECT TIMINGS

  

May 21, 2010 RFP for Phase 2 issued
May 27, 2010

Society Incorporated by Province of Alberta

June 10, 2010 Site visit for Phase 2 RFP
June 21, 2010 Proposals in response to Phase 2 RFP due by 2:00PM
July 5, 2010 Winning Proposal selected
August 9, 2010 Winning Proposal Announced
October 15, 2010

Preliminary design released to public at Centre 2000

October 31, 2010 Overall project funding to be secured
February 1, 2011 Final design drawings for Phase 2 submitted for review and approval
March 1, 2011 Commence tendering for Phases 3 and 4
March 31, 2011 Completion of Phase 1
December 31, 2012 Completion of Phases 3 and 4